The cement pad (footing) was poured again today, but instead of pouring to the West, it was poured to the South. Mike has been notified. The siding was worked on but not completed as they ran out of material. The interior walls were firred out or in where needed. I also notified mike that the french doors are real tight at the top now.

I looked up online and fire sprinkler systems are roughly $1 per square foor in new construction, so I assume it will be $2-3k for the installation of them. ...fuck!