Monday, April 23, 2007

2007 04 23

Friday the siding was worked on but they cut out early as it started to rain. The cement pad under the hous for the footing was done on Friday but as I let Mike know, it is offset off the bean by about a foot. The crawlspace entrance was also done on Friday.

This past weekend (2007-04-20 through 22, Megan, Jim, Pat, & I framed out the bathroom pony wall for hanging stuff, the walking closet walls were also shored up with 2x6s as the doorway is there. I got the attic sheets loose and ran more wires for cameras and speaker wire. I also got the kitchen almost sheeted.

Today (2007-04-23) the framers are back and are working on the siding.