Jackson came back with $3700 and I balked at that asking what they could do. He came back the next afternoon (Wednesday the 21st of Feb) and told us $3100. We agreed. Mike called me up and stated it may rain Thursday/Friday (is sprinkled) and so they would be starting back up on Monday the 26th of Feb.

So if they do actually start today, they will need to go down further on the slab area and the footings, then compact the area, lay the gravel and then the rebar... then the inspection can be done so the slab can be poured.