Thursday, January 25, 2007

2007 01 25

I will go back in my e-mails and find all the initially listed dates, then I will continue to date what is done every day until we have the final inspection.

list date from when we started talking
list date from when plans were drawn
list date from when plans done
list the dates of the back and forth nonsense of the plans finally making it to final permit
list the date of the permits complete

2006 01 22 - Day 1, demo of kitchen walls, kitchen flooring, and all the cabinets except for the kitchen sink
2006 01 23 - Day 2, demo of exterior walls and office
2006 01 24 - Day 3, removal of the slab and the office slab
2006 01 25 - Day 4, digging of the footing, setting of the forms - I arrived and discovered the height to be incorrect. I spoke to Jackson on my cell phone at 7:30 PM. Jackson will look at it himself on Saturday the 27th in person. I left a vm with Mike at 3:34 PM today but he has not called back yet, its 8:01 PM right now. The foreman at the site today, told us he did not see an elevation on the drawing and "just set the form at a step or two". The drawing specifically calls out on sheet A4 for Section F to have two elevations (one being the existing kitchen height and the other being the proposed living room floor height) with two steps in between. Jackson said he will stop the job until this is resolved and that there is nothing planned for tomorrow anyway.