Monday, December 31, 2007
2007 12 31
Next Tuesday Mike and Jackson will be here to close out the project and get thier last check. That will be ccol for them to see all the work I have done in the past 5 months as the last thing they really did was get the drywall on and I did 99% of the finish.
Friday, December 28, 2007
2007 12 28
Tuesday, December 25, 2007
2007 12 25
Saturday, December 22, 2007
2007 12 22
I have completed the bedroom flooring and last night I laid down the moisture barrier in the living room. Right now I am setting up the first strip against the north wall of the living room to run all the other boards off. Hopefully the living room will go quickly and it will get done today or tomorrow. Yesterday we ordered a new bed, mattress and nightstands from Mor and it should be here Monday the 31st. That was $3400... ouch!
I bought a router and a router table so I can use the scrap from the flooring as we are going to run out of flooring. I am using it to create a tongue on some board ends and groves on others. I picked up 4 boxes of comparable flooring from Lumber Liquidators and it matches up pretty good. We had to go with different stuff as Turion is no longer in business, which is the first kind of flooring we bought. So much for having a 30 year warranty on the flooring...
All next week I will be finishing off stuff like baseboards and grouting the kitchen floor tiles, touch up paint and things like that.
The shower enclosure got installed on Wednesday and it looks awesome. It was a huge amount of money but it really makes the whole room look great.
Sunday, December 16, 2007
2007 12 16
I started on the bamboo flooring and now I can see why installers can charge so much. First I had to find all the low spots and fill them in with Henrys 547 UniPro Universal Patch & Skimcoat. Then I layed down a layer of Bostiks MVP4 Moisture Barrier and let it sit overnight. I woke up to find it still tacky but that is what Lumber Liquidators said it would end up like. As long as you can walk on it and it does not transfer to your shoes, you are good to go. So then I layed down the Bostick Best flooring adhesive, enough so I could reach at at time and started to lay the bamboo boards. It took most of the day to do all of this and it looks great. Sometime this week I would imagine we will be going to Mor Furniture to get the bed we saw and liked. It is a little over the top but will go well with the addition and will be a much nicer bed than what we have. Hopefully we can get rid of that one and make a few dollars as it was $1200 and the mattress was about a grand too.
Tuesday, December 4, 2007
2007 12 04
I got another light replace on the outside of the house. It has not worked for the past several weeks and lw and behold when I wen to remove it, the top was exposed 1/4" or more so water has been getting in there during the rains with high winds. To boot the ground wire was not connected from the light to the bar, which is grounded. I assume both lights on the East side of the house have burned up for the same reasons. Horray for the Lars subs installing them properly. They were only $20 each... fagetaboutit. It would be far more hassle to try and retrieve the money.
I spent a hour or two cleaning up the bathroom tiles as I have made a mess of them in the pastr month or two with mortar, grout, paint and silicone. They look great now and things like the toe kick are ready to go in. I plan on getting the kitchen floor halfway grouted tonight. That is if I have time after I pick up our safe from the trucking company and get it home. Eric is gonna follow me home and we are going to try to get it out of my truck and into the house. We shall see... it should not be too bad as it is only 450 lbs.
Saturday, December 1, 2007
2007 11 30
Friday, November 30, 2007
2007 11 29
Tuesday, November 27, 2007
2007 11 27
The final inspection failed as we thought, but at least we only failed on known items; the jacuzzi access cover, the canned light trim in the bedroom, the anti siphon set screw on the hose bibs, and the shower enclosure. I took last week off and got the bedroom painting completed so now all the vents, lights and covers are up. Mike stopped by last Wednesday with the jacuzzi access cover and I just mounted it with adhesive silicone. I also go the shower tiles pretty much completed except for the bottom row. It has to be done in multiple stages the way I am doing it, so as to make it as waterproof as possible. Half of the shower floor got grouted last night and I will finish it off tonight. That leaves the bottom row of granite tiles and the threshold. and then finally we can have the shower doors accurately measured. That is gonna cost over $1500. Ouch...
In the past two week since I have last entered more information into this blog, I have also done a lot of cleanup outside and so has Megan, doing a little bit of yard work. I built up the dirt area at the bottom of the back steps, pretty much finished the stair tiles leading into the living room, bought and installed most of the closet cabinetry after painting the closet a bright white, mounted the vanity lights, the medicine cabinets, finished the jacuzzi granite tiling, tiled most of the desk bullnose, the bedroom pony wall moulding, spackeled and sanded half or so of the crown moulding, and of course took the day off to eat my share of the decapitated and disemboweled bird.
I hope to get crackin on the hardwood floor in about two weeks, we shall see. The only thing holding me up is the shower, so I can get the glass on order, and of course getting the bedroom doors completed as they need additional coats of polyurethane.
Monday, November 12, 2007
2007 11 12
I have a fair amount of stuff to be done but it was a big thing to finally get the shower grouted. The floor looks great grouted and I can't wait till I can get the kitchen floor grouted too as it looks way better. The closet needs to be caulked at the bottom of the sheetrock as we are thinking of skipping the baseboards in the closet to get the cabinetry we buy, butted up against the wall. We just need to paint in there and then we can get the cabinetry. We are thinking of getting the dark cherry looking stuff from Lowes but will look at Ikea first.
Friday, November 9, 2007
2007 11 09
2007 11 09
I got lazy this last week or two, in moving back into the house... kind of taking a break but finishing off the last few things is really a royal pain. I should have most of the tiling finished off tonight in my drunken stupor and hope it does not look like shit too much.
Tomorrow I should spend the majority of the day trying to get things ready for final inspection next week so here goes nothing...
Hopefully the laying of bamboo flooring will be nothing like the nightmare that the tile has become. To boot there is only 800 square feet of bamboo flooring I need to lay!
Thursday, November 8, 2007
2007 11 08
Mike is also going to have the electricians come check out the dishwasher electrical line as it is not hot. Mike is going to call for the final inspection next week and that will most likly get them off the hook for anything remaining and they can get their last check. That will leave me with a list of to dos, mostly consisting of the bathroom as stuff like the hardwood flooring will not need to be in to pass inspection.
I discovered the transom window above the french doors is broken. Only the outside pane is broken and I could not see anyhting around that cold have broken it as it is way too high off the ground. I know it got broken yesterday and the day before I was on a ladder a few feet from it on the inside of the house installing a ceiling speaker so I would have seen it then. It must have been defective, installed improperly or someone slammed the french doors and is not fessing up.
Monday, November 5, 2007
2007 11 05
Friday, November 2, 2007
2007 11 02
Thursday, November 1, 2007
2007 11 01
Monday, October 29, 2007
2007 10 29
Sunday, October 28, 2007
2007 10 28
Saturday, October 27, 2007
2007 10 27
Friday, October 26, 2007
2007 10 26
Thursday, October 25, 2007
2007 10 25
Wednesday, October 24, 2007
2007 10 24
Tuesday, October 23, 2007
2007 10 23
Monday, October 22, 2007
2007 10 22
Sunday, October 21, 2007
2007 10 21
Saturday, October 20, 2007
2007 10 20
Sunday, October 14, 2007
2007 10 14
Friday, October 12, 2007
2007 10 12
Thursday, October 11, 2007
2007 10 11
This weekend I wll be getting the floor tiles completed and grout the floor tiles and finish off the small stuff like the crown molding.
Monday, October 8, 2007
2007 10 08
Friday, October 5, 2007
2007 10 05
Sunday, September 30, 2007
2007 09 30
Monday, September 17, 2007
2007 09 17
Tuesday, September 11, 2007
2007 09 11
Wednesday, August 22, 2007
2007 08 22
Tuesday, August 14, 2007
2007 08 14
Thursday, August 9, 2007
2007 08 09
Wednesday, August 1, 2007
2007 08 01
Wednesday, July 25, 2007
2007 07 25
Friday, July 20, 2007
2007 07 20
Tuesday, July 17, 2007
Wednesday, July 11, 2007
2007 07 11
Tuesday, July 3, 2007
2007 07 03
Wednesday, June 20, 2007
2007 06 20
2007 06 20
Mike also asked about the tub rough-in stuff which I told him was in the bathroom.
Monday, June 18, 2007
2007 06 18
The final framing inspection is supposed to occur today. That is where the plans must be as they are missing from the house.
We go the fascia/flashing painted white, two coats West and South, one coat East and none on the North. We go the old shit windows painted flat and will come back with semi-gloss this weekend in addition to doing the dark green.
Thursday, June 14, 2007
2007 06 14
Tuesday, June 12, 2007
2007 06 12
Monday, June 4, 2007
2007 06 04
Thursday, May 31, 2007
2007 05 31
Wednesday, May 30, 2007
2007 05 30
Tuesday, May 29, 2007
2007 05 29
Wednesday, May 16, 2007
2007 05 16
Mike will also get on the missing cement landing and the trash can pad out front. He balked and said it would be best to wait until the end but I said they look like shit so he said he will get on it. Mike also said he will have Symons place the fire sprinkler shutoff valve box on the north side of the house near the water heater area. He said once the plans are approved, he will ask them to place their tie in to the 1 1/4" line so I will still have room for me to install a pressure regulator. In fact I will email him right now and ask if I can buy the pressure regulator, leave it at the house and have Symons install it for me as it will only be a couple of extra joints to sweat.
We agreed there is no reason to have him drive up tomorrow so I'll also send him an email to approve that.
Tuesday, May 15, 2007
2007 05 15
Thursday, May 10, 2007
2007 05 10
2007 05 10
Monday, May 7, 2007
2007 05 07
Friday, May 4, 2007
2007 05 04
Mike is going to have the electricians re-mount the security light above Trins windows, and someone will be mounting the kitchen porch light. Extreme Roofing will be installing the four addition dormers and possibly two more instead of my thermostatically controlled fan based upon price. They will also be installing flashing where the kitchen vent pipe is, and where I am mounting a shower exhaust fan this weekend. For $50, Viking Electric will be wiring it to the jacuzzi tub area switches... and will be installing a double switch. I'll take care of the french door opening as the doors no longer hit the siding. Someone from Lars or Milgard will also be moving the tempered window to the bedroom door area as it is in the wrong spot.
To Do's for this weekend
Finish wiring once and for all
Mount a 2x4 at the ends of the "deck" railing so Trin does not bump her head on the pointed edge
move blue tarp to dumpster
move wood and siding into garage
re-cover race car, it looks like shit
purchase and install bathroom exhaust fan
anything else?
Wednesday, May 2, 2007
2007 05 02
Monday, April 30, 2007
2007 04 30
Thursday, April 26, 2007
2007 04 26
Wednesday, April 25, 2007
2007 04 25
I looked up online and fire sprinkler systems are roughly $1 per square foor in new construction, so I assume it will be $2-3k for the installation of them. ...fuck!
2007 04 25
Mike called me yesterday afternoon and said his sprinkler guy is out for a week so he will see if he can find someone else to bid the job.
Tuesday, April 24, 2007
2007 04 24
Monday, April 23, 2007
2007 04 23
This past weekend (2007-04-20 through 22, Megan, Jim, Pat, & I framed out the bathroom pony wall for hanging stuff, the walking closet walls were also shored up with 2x6s as the doorway is there. I got the attic sheets loose and ran more wires for cameras and speaker wire. I also got the kitchen almost sheeted.
Today (2007-04-23) the framers are back and are working on the siding.
Thursday, April 19, 2007
2007 04 19
The shower pan was hot mopped today. The new bathroom toilet service line was move today but again it needs to be moved as it will be too high. The from service line to the house was replaced, the 5 or so feet of it that was damaged when the sewage line was replaced. The gas line was run to the laundry center and the kitchen vent pipe was run. A house block was under the house but it was crooked and it sunk into the ground from the pressure of the block above it with the joist resting on it. Now Mike is having a 20x20x12 cement block placed and that will have wood bottle jacked into place.
I reminded Mike we are getting rounded corners instead of square ones, for some reason he had told the drywallers square. Mike said the pony wall will stiffen up with the drywall, I will see about doing some red heads this weekend. Mike asked that I raise the sheets in the attic to allow the insulation to be installed. The shower valve did not show up today when we had Pat bring all the plumbing fixtures over from the house.
Mike asked me to get the exterior lights, the ceiling fan for the living room, the vanity cabinet overhead lights.
The siding is going on today with Derek, Brandon and Riley. They got the trim done and the bottom three rows on the back and south side of the house. Derek suggested that I caulk every possible crack on the siding to make it a moisture barrier... bugs too.
The framing inspection will be done on Monday which will allow the drywall to start. The electricians will button up after the drywall is done.
2007 04 19
Wednesday, April 18, 2007
2007 04 18
Tuesday, April 17, 2007
2007 04 17
2007 04 17
Thursday, April 12, 2007
2007 04 12
Kitchen
2x6s in stud bays to hang cabinets - Mike said this is fine for me to do
Kitchen window crack - Mike said he would have the window replaced
Stucco around kitchen window - Mike said he will have it covered with stucco
Kitchen door does not close easily - Mike will have the edge surfaced so the door closes properly
Kitchen plumbing finish - Mike said in the next couple days, before the drywall of course
Laundry gas line and lint vent exit to outside - Mike said it will get done
Extra canned light - We bought one at Lowes this afternoon and took it back to the house, it will be installed tomorrow per Luis
Living Room
Show Mike the poorly manufactured windows - Veronica said she will get me the warranty info tomorrow. Mike said he will get the windows fixed/replaced
Window sash - Mike will get it fixed
Finishing of the french doors - We will get a cheap lock set on this weekend and Mike will have the finish set installed when the job is done, I will try to get a piece of pipe set for the pegs instead of just drilling a hole into the wood frame
Bedroom
Shore up pony wall in bedroom before drywall - Mike is having two bolts put through bottom plate into the cement
Toilet pipe re-routing - Mike will have it re-routed so it comes out the North wall instead of out of our granite
Bathroom medicine cabinet lights - We will buy them and leave them at the house for them to be installed by a sub
Shower niches - Mike will have one fire break removed so we can freely place the shower niche
Outside / Other
North roof transition line is bad looking - It does not look as bad today, it may have been flattened out by the guys walking on it
Cement slab out front - Mike is going to have it fixed
Cleanout under kitchen window - I will fix it myself
Attic fan to be reinstalled - I will mark the location with upside down paint and Mike will have it installed on the North side of the house
Plates over wires - Will only be installed where the wires are not in the center of the studs, I will put some more on this weekend
Water service line to the house - Mike said it will be completed (the exposed/damaged area by the fence)
Crawlspace access - Mike said the hole will be accessable via a wood frame covered with screen. The outer area will be cement like a dam.
The AC unit placement - Dirt still needs to be sloped away from the house so the pad for the AC unit can be placed, I will move it later so it will be out of the way
Sub-Panel location - Unit will be wired via the walls and attic. unit will be flush mounted on the outside of the house so it will not interfere with our shower niches
Cement for missing step on south side of the house - Mike said it will be done at the end of the job, along with the cement in the living room where the steps were not poured close enough to meet with the wall
2007 04 12
Wednesday, April 11, 2007
2007 04 11
2007 04 11
Mike said the cement pad will be fixed and that it was idiotic that the driver drove over it. He said it will be fixed at the end of the job when other cement work is done. He said the asphalt was already in poor condition and that Jackson and I can deal with it at the end.
The roof looked finished on the south side this morning so that will be done today it looks like and the HVAC guys are supposed to button up today too. I would imagine Derek will start papering and siding Thursday then.
Mike and I said we are still on for our scheduled Thursday meeting.
2007 04 11
The HVAC guys should be done today. Maybe the roofers, plumbers, or framers will show up today.
Tuesday, April 10, 2007
2007 04 10
Sunday, April 8, 2007
2007 04 08
Thursday, April 5, 2007
2007 04 05
In case I did not note it before, we had 34 yards of concrete poured for the slab... wow.
2007 04 05
During todays meeting I will show Mike the pony wall in the bedroom, the scratches on the hardwood floor and the buckle in Trinitys room. Jackson said he will try to make it out today. He said they will also be paying the $500+ for the additional panel. Nothing was said about the additional $2125 so I assume it will be added to the next scheduled payment. Jackson said they should be out of there in about two weeks so very soon we will be working our ass off at the house, installing all kinds of stuff :-)
Wednesday, April 4, 2007
2007 04 04
Jacksons stand in the last conversation is that he does not want us to have to spend the next possibly couple or more weekends rewiring the house. He said we should not have to pay for the additional box needed for circuitry or the run to it. He also added that he had an arguement with Mike so I assume there was some disaggreement about who should pay for what.
Whatever the case, we are getting a lot more electrical stuff than we had originally paid for and we are paying half for what it would normally cost.
I ordered four in ceiling speakers today from eBay and will order more if they turn out to be good. They pop into holes made after the drywall is up and are held in place by brackets that pivot out and pinch the back of the drywall.
2007 04 04
Derek just called and asked about the exposure of the siding we picked which was the James Hardie Hardie Plank Colonial Roughsawn which is 8" wide (tall) 12' long and 5/16" thick. It has an exposure of 6.75". He asked about trim sizing and I could not find it on the web but he said it should be around 3/4" x 3.5" which sounds about right based upon what we saw at Dixieline.
Tuesday, April 3, 2007
2007 04 03
Monday, April 2, 2007
2007 04 02
Sunday, April 1, 2007
2007 04 01
Saturday, March 31, 2007
2007 03 31
Derek, Brandon and another gut started on the soffit today. The did the medicine cabinet area, extended the laundry center, built the tub area, the bedroom pony wall and the shower area. the moved living room wall area was also sheeted/sheered. Also the new window in Trins room was framed and the east wall in her room was furred out. Next week the windows should be in and the next inspection should be done. That means in the next two weeks or so the drywall should be done. We got the canned lights and the french doors. The bamboo flooring is in and we will pick it up Monday.
The old furnace was removed and the hole was sheeted yesterday. The pony wall in the living room is much better now that I have it sheered. Just gotta figure out what to do with the bedroom pony wall to strengthen it. I got a new 4 port video card and will have additional cameras set up soon too. We will pick out siding tomorrow and it looks like based upon Derek told me, composite is the way to go.
Friday, March 30, 2007
2007 03 30
This weekend we have these for "to do's":
for sure
move the laundry center soffit line out 3/4"
make a decision on siding
make a decision on canned lighting (have Don confirm next week and then purchase?)pick up french doorssheet area around pony wall and sheet pony wallget second camera going
if we have time... as the above will take most of Saturday plus possibly some of Sunday
mow lawn and weed whackclean truck
Thursday, March 29, 2007
2007 03 29
Today Mike sprayed for the J bolts that need to be added to the bottom plates. He also maked various things like the back of the house around where the window moved; to be sheeted and the laundry center to be moved out. I just snt him an email about the soffit going to need that same bump too. The attic access is going to go in between the two canned lights in the walk in closet. Mike said I can use whatever wood I want to shore up the pony wall. Maybe I should ask him if I can use some more of the wood to sheet the bedroom pony wall as I am worried about it wobbleing after time.
We met with Don the electrican today. He instructed us to get the pony wall completed so he can run the electrical through it. We are also to pick up 14 low volt ICT canned lights (HALO - 50 watt MR16). He told me to get "silve ones and not the white ones" as I need to get ones that can have insulation go right over them.
I forgot to ask Don about doing a phone line in the master bedroom. I will include that with the FAX I send him tomorrow as he wants the cabinetry plans and the bedroom bed placement.
Bedroom Electrical
two lights over our bed on both sides with switches on both sides that operate one or both
two lights over the vanity sinks
one light over the shower
one light over the tub
two GFCI outlets in between the two sinks
two lights in the walk in closet
two or lights in line with the four bedroom windows
switches will go east of the tub on the southern tub wall
fan in the middle of the room operated by its own switch
there is going to be cable run to the south bedroom wall up about eye level with an outlet, below it will be a run it is connected to sop a flat panel will have no cables going to it - it will also have a feed that runs to the walk in closet so we can later add a flat panel near the jacuzzi tub
outlets on all walls off the floor per code with one or two on the bedroom pony wall
Living Room Electrical
Three way outlets at the bedroom door, north stairs and southern wall door which will operate the rooms canned lights
three lights in line with the east wall windows
two lights where the DVD rack or fish tank will be going
no lights above the entertainment center
two lights above the desk
a fan in the middle of the room
outlets all around the room with a dedicated 20 amp two 4 gang outlets for the computer area
one four gang outlet for the entertainment center
Kitchen
three way switches at the sourthern wall doorway, the north stairs and the west entrance
one light in the laundry center enslosure
two hanging lights above the island
two or three by the oven wall
two by the sink wall
two or three by refridgerator wall
outlets for the fridge, microwave, hood, stove, island fridge, garbage disposal, and dishwasher
GFCI outlets all around per code
outlets on the pony wall
two outlets in the island
I'll also add to the FAX to Don that we want a cable run to the southern wall of kitchen, in the corner
Old Living Room
The double switch outlet that now resides in the new laundry room center is going to be moved to the old living room
Trinity's Room
Two outlets on her east wall as they touched it, or the addition of the double outlet that also used to service the office area
Wednesday, March 28, 2007
2007 03 28
Tuesday, March 27, 2007
2007 03 27
Monday, March 26, 2007
2007 03 26
Mike responded that it should be okay about my email about the pony walls and the sheetin of the kitchen floor. He said its cool to do this weekend but I'd like to talk to him about it first in person this Thursday and I'd like to first have the plumbing and electrical moved out of the way.
Saturday, March 24, 2007
2007 02 24
Today the old dinning room ceiling was removed and the kitchen window was removed.
Friday, March 23, 2007
2007 03 23
The roof sheeting has been completed. Mike and I completed the soffit layout yesterday and the west wall of the living room will be used as the soffit start. We will have a 3.5" soffit all the way around the kitchen cabinets and wall areas. The kitchen opening is going to be closed up per the plans as the west entrance to the kitchen is going to be 4', not the 8' or so that it currently is. Derek will be extending the laundry center by 3" to make it deeper and also have it be 40" outside to outside dimensions. The inspector will need to know the 4x4 holding the west end of the beam is supported well, so Mike will need to get images to him. I'll also check it out myself.
The cavity under the kitchen where the office used to be is going to be filled with insulation. The new bathroom medicine cabinets are going to be set centered on our sinks and at a normal height... centered more or less on my face. The kitchen window was measured and ordered incorrectly and Mike stated we would not be paying for it. We will layout electrical next week is sparky is there.
The plaster in the kitchen is going to be removed to make the matching go easier. The east wall in Trins room is going to be furred out ~1" as the ceiling drop in our new bathroom protrudes into her ceiling. This way we do not have to do crown in there or double the drywall. The pony wall in between the living room and kitchen is going to now be 36" instead 42.
Derek had a good idea... to bolt the desks to the pony wall, which will help to stabilize it; otherwise it will get loose over the years. Trinity's second window is going to be set at the same header height, protruding down ~5" lower than the old one in her room, which I will be doing later. It is going to be set with the same reveal as the old window which is ~14" from the wall.
Thursday, March 22, 2007
2007 03 22
Today we are supposed to lay out (snap the lines) the soffit/coffered ceiling with Mike and if time permits, walk the electrical.
Tuesday, March 20, 2007
2007 03 20
They said they should be done sheeting in the next day or two, do the flooring where the office was and then onto the new bathroom area.
Its gonna rain tonight so last night and today they tarped off the roof.
Monday, March 19, 2007
2007 03 19
Saturday, March 17, 2007
2007 03 17
I called Mike and he was aware and said he will go back to Jackson and possibly the architect, as I told him a post was unacceptable.
Jackosn had previously confirmed last week that we had $1100 allocated in our remodel budget for a beam. the whole point of a beam is to hold weight over a span, not half ass it with a post. Come on now, this is not a tree fort...
Friday, March 16, 2007
2007 03 16
The shit for brains architect did not investigate the top plate height and due to the roof pitch and the fact that he decided to go with trusses instead of a conventional roof. When we got to the house for our Thursday meeting yesterday (2007 03 15), we saw that they were removing all the existing top plate and having to cut down 3 inches (thickness of two 2x4s) to drop the ceiling. This is being done so the trusses will fit.
Instead of making them waste the trusses I decided to settle on either raising the roof the couple inches or dropping the ceiling a couple inches. The end decision is to drop the addition ceiling a couple inches and going into the kitchen a little bit, then it will bump back up a couple inches to the existing ceiling height. The soffit will follow the cabintry lines so next week or the one there after, Mike and I will snap lines to get the soffit area built.
Wednesday, March 14, 2007
2007 03 14
Monday, March 12, 2007
2007 03 12
They are ripping the roof off today to prepare for the trusses, and they are removeing interior walls.
Friday, March 9, 2007
2007 03 09
Mike called me and said part of the celing in Trins room is gonna have to come down as they need to tie into a beam that is a couple feet into the ceiling from the East wall. Looks like Megan is gonna get her wish about re-doing Trins room.
2007 03 09
Thursday, March 8, 2007
2007 03 08
2007 03 08
He says they should have wood delivered tomorrow and should start framing. We went over the closet extension, the pony walls for the shower to be 42", the other pony walls to be 36". The north wall of the closet may move a couple inches south to accomodate the shower being made square. The pony wall seperating the bedroom may move a couple inches east for toilet codes. The heater unit will be placed out of the way of bringing stuff into the attic.
Tuesday, March 6, 2007
2007 03 06
The guys that laid the gravel made a mess in the front yard on top of the area I park my truck. There is now what looks like, several hundred pounds of gravel on top of the bark I paid for just a couple months before the remodel began.
Monday, March 5, 2007
2007 03 05
Rebar has been laid in the stem walls and drilled/epoxied into the existing footings. Looks like gravel can be done and then the rebar. If they every get two consecutive things done correctly we will finally pour sometime soon.
Thursday, March 1, 2007
2007 03 01
2007 03 01
Tuesday, February 27, 2007
2007 02 27
Monday, February 26, 2007
2007 02 26
So if they do actually start today, they will need to go down further on the slab area and the footings, then compact the area, lay the gravel and then the rebar... then the inspection can be done so the slab can be poured.
Tuesday, February 20, 2007
2007 02 20
Monday, February 19, 2007
2007 02 19
Thursday, February 15, 2007
2007 02 15
Sunday, February 11, 2007
2007 02 11
Thursday, February 8, 2007
2007 02 08
Mark Noyce saw the form, told John who told me, I talked to Mark and had him explain what he thought. He has built many houses in the neighborhood and all have cracked slabs to some degree. In order not have a badly cracked slab the county code calls for 6" of crushed gravel on top of soil compacted to 90%. The a sheet of visqueen/plastic as a moisture barrier to keep the xpansive soil (clay) from cracking the slab. On top of that 2-3 inches of sand. Also wetting it for several days is also supposed to be good.
Mark showed me how easily a spike goes into the ground in some areas which means it is not compacted. Mike is getting a quote from jackson on how much it will be to add the gravel and build per a "clay soil detail". Somehow these fucktards did not see that it was clay when it was fairly obvious to my untrained non-construction eye that there is clay. Somehow they did not bill for it so we are looking at potentially a fat chunk of money to get it done right versus getting the way they had planned which is not for expansive soil.
A way to fix the area without going down further Mark suggested is to add a 2x6 on top of the existing form perimeter which would allow for the 6" of crushed gravel. To boot, the steps into the living room could be reduced to 5" steps instead of 8" which would still give us 3 steps. This measn the plumbing drain boxes (x2) need to be raised in the proposed bathroom area. This would be by far the cheapest way to go, but then reduces our ceilingsfrom 9' 9" to 9' 3" or so... fuck.
Wednesday, February 7, 2007
2007 02 07
Monday, February 5, 2007
2007 02 05
Friday the 2nd the remaining plumbing was completed, including the bathroom plumbing
Saturday the inspector showed up a day late to inspect the plumbing which was approved
Monday the 5th, Mike tells me the plumbers did not damaged the water service line to the house which is damaged and looks like the damage is fresh, he said he will look at it tomorrow and get back to me
supposedly the slab should be poured this week, for some reason however the dirt in the back yard has not been compacted, I guess it is compact enough as it is or it is being skipped due to Lars being cheap... we shall see how badly the slab cracks
Tuesday, January 30, 2007
2007 01 30
Monday, January 29, 2007
2007 01 29
Saturday, January 27, 2007
2007 01 27
Just to let you know everything including the sewer will work out as per plan. We will be correcting the problem on Mon. 29th. We will also be digging up the sewer on Mon. I told the concrete contractor to make 3 7-1/2" steps. This will drop the room 22-1/2" giving you 9'9" plus. We will probably be removing the water heater so we can ge to the sewer claen out that is right there. If we do remove the water heater the house will be without hot water for some time.
Friday, January 26, 2007
2007 01 26
Thursday, January 25, 2007
2007 01 25
list date from when we started talking
list date from when plans were drawn
list date from when plans done
list the dates of the back and forth nonsense of the plans finally making it to final permit
list the date of the permits complete
2006 01 22 - Day 1, demo of kitchen walls, kitchen flooring, and all the cabinets except for the kitchen sink
2006 01 23 - Day 2, demo of exterior walls and office
2006 01 24 - Day 3, removal of the slab and the office slab
2006 01 25 - Day 4, digging of the footing, setting of the forms - I arrived and discovered the height to be incorrect. I spoke to Jackson on my cell phone at 7:30 PM. Jackson will look at it himself on Saturday the 27th in person. I left a vm with Mike at 3:34 PM today but he has not called back yet, its 8:01 PM right now. The foreman at the site today, told us he did not see an elevation on the drawing and "just set the form at a step or two". The drawing specifically calls out on sheet A4 for Section F to have two elevations (one being the existing kitchen height and the other being the proposed living room floor height) with two steps in between. Jackson said he will stop the job until this is resolved and that there is nothing planned for tomorrow anyway.