Tuesday, August 14, 2007

2007 08 14

Last Friday the grading was completed which included them removing the gravel from out front and leveling the pile removed from the north side of the house. We painted this weekend, getting the kitchen and living room primmed, the kitchen painted and some of the living room. Last Saturday the windows were cleaned and they look brand new. Yesterday, Monday the 13th, the fire inspector came out and failed us twice as the fire system was not going off consistantly or under the specified time frame. Under 60 sec is a req. apparently, but the inspector wanted 30 seconds. We finally were getting that after he left and the second guy from Symons Fire Protection showed up. The next inspection is set for this coming Friday. Mike said bark will be laid down and now that the grading has been completed, the AC unit can be installed and the HVAC completed.